A kill switch is a logical relationship that exists between the project tasks, or between a project task and a milestone.

A) True
B) False

Correct Answer

verifed

verified

What is the logical relationship that exists between the project tasks, or between a project task and a milestone?


A) resource
B) task
C) dependency
D) activity

E) All of the above
F) C) and D)

Correct Answer

verifed

verified

What is the process of transferring information from a legacy system to a new system?


A) COBIT
B) conversion
C) business requirements
D) sign-off

E) None of the above
F) A) and B)

Correct Answer

verifed

verified

What is a common approach using the professional expertise within an organization to develop and maintain the organization's information technology systems?


A) In-sourcing
B) Outsourcing
C) Business process outsourcing
D) Offshore outsourcing

E) A) and D)
F) B) and C)

Correct Answer

verifed

verified

Which machine language is difficult for people to understand?


A) first generation machine language
B) fifth generation machine language
C) third generation machine language
D) fourth generation machine language

E) B) and D)
F) None of the above

Correct Answer

verifed

verified

Which of the following is not a characteristic of a well-defined project plan?


A) prepared by the project manager
B) easy to read
C) appropriate to the project's size
D) communicated to all key participants

E) A) and D)
F) C) and D)

Correct Answer

verifed

verified

Plunge implementation is a set of policies, procedures, standards, processes, practices, tools, techniques, and tasks that people apply to technical and management challenges.

A) True
B) False

Correct Answer

verifed

verified

Which programming language looks similar to human languages?


A) first generation machine language
B) second generation machine language
C) third generation machine language
D) fourth generation machine language

E) A) and C)
F) A) and B)

Correct Answer

verifed

verified

What is the overall process for developing information systems from planning and analysis through implementation and maintenance?


A) systems development life cycle
B) project management
C) systems management
D) project development life cycle

E) A) and D)
F) All of the above

Correct Answer

verifed

verified

Business requirements are the specific business requests the system must meet to be successful, so the analysis phase is critical because business requirements drive the entire systems development effort.

A) True
B) False

Correct Answer

verifed

verified

An SOA service is simply a business task, such as checking a potential customer's credit rating when opening a new account.

A) True
B) False

Correct Answer

verifed

verified

Nearshore outsourcing occurs when organizations from developing countries are used to write code and develop systems.In offshore outsourcing the country is geographically far away.

A) True
B) False

Correct Answer

verifed

verified

Iterative development consists of a series of tiny projects.It has become the foundation of multiple agile methodologies.

A) True
B) False

Correct Answer

verifed

verified

A dependency is a trigger that enables a project manager to close the project before completion.

A) True
B) False

Correct Answer

verifed

verified

What makes system changes to repair design flaws, coding errors, or implementation issues?


A) corrective maintenance
B) preventative maintenance
C) pilot implementation
D) phased implementation

E) All of the above
F) A) and D)

Correct Answer

verifed

verified

Describe the seven phases of the systems development life cycle.

Correct Answer

verifed

verified

Planning phase-involves establishing a h...

View Answer

Rational unified process (RUP) methodology, owned by IBM, provides a framework for breaking down the development of software into four "gates"

A) True
B) False

Correct Answer

verifed

verified

The design phase establishes descriptions of the desired features and operations of the system including screen layouts, business rules, process diagrams, pseudo code, and other documentation.

A) True
B) False

Correct Answer

verifed

verified

Which assembly language is difficult for people to understand?


A) fifth generation machine language
B) second generation machine language
C) third generation machine language
D) fourth generation machine language

E) B) and D)
F) B) and C)

Correct Answer

verifed

verified

What do software engineers use as tools to provide automated support for the development of the system?


A) software
B) IEEE
C) COBIT
D) CASE

E) C) and D)
F) B) and D)

Correct Answer

verifed

verified