Filters
Question type

Study Flashcards

_____________ training is held in a classroom environment and led by an instructor.

Correct Answer

verifed

verified

Which of the following is the primary reason why companies outsource?


A) Tap outside sources of expertise
B) Concentrate resources on core business
C) Reduce headcount and related expenses
D) Better manage the costs of internal processes

E) C) and D)
F) A) and B)

Correct Answer

verifed

verified

What makes system changes to reduce the chance of future system failure?


A) Corrective maintenance
B) Preventative maintenance
C) Pilot implementation
D) Phased implementation

E) All of the above
F) B) and D)

Correct Answer

verifed

verified

Which of the following is a benefit an organization can receive from outsourcing?


A) Financial savings
B) Increase technical abilities
C) Market agility
D) All of the above

E) A) and C)
F) A) and D)

Correct Answer

verifed

verified

What are factors considered to be true,real,or certain without proof or demonstration?


A) Project plan
B) Project constraints
C) Project assumptions
D) Project deliverable

E) B) and C)
F) A) and D)

Correct Answer

verifed

verified

A dependency is a logical relationship that exists between the project tasks,or between a project task and a milestone.

A) True
B) False

Correct Answer

verifed

verified

What is a simple bar chart that depicts project tasks against a calendar?


A) Gantt chart
B) PERT chart
C) Dependency
D) All of the above

E) C) and D)
F) B) and C)

Correct Answer

verifed

verified

What are project assumptions?


A) Specific factors that can limit options
B) Factors that are considered to be true,real,or certain without proof or demonstration
C) Quantifiable criteria that must be met for the project to be considered a success
D) A document issued by the project initiator or sponsor that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities

E) A) and D)
F) None of the above

Correct Answer

verifed

verified

Project assumptions represent key dates when a certain group of activities must be performed.

A) True
B) False

Correct Answer

verifed

verified

What verifies that the units or pieces of code function correctly when integrated together?


A) Alpha testing
B) Development testing
C) Integration testing
D) System testing

E) A) and D)
F) All of the above

Correct Answer

verifed

verified

____________ acceptance testing (UAT)determines if the system satisfies the user and business requirements.

Correct Answer

verifed

verified

User acceptance testing (UAT)determines if the system satisfies the user and business requirements.

A) True
B) False

Correct Answer

verifed

verified

What type of chart typically displays the critical path?


A) Gantt chart
B) PERT chart
C) All of the above
D) None of the above

E) A) and B)
F) None of the above

Correct Answer

verifed

verified

Showing 281 - 293 of 293

Related Exams

Show Answer