_____________ implementation installs the new system in phases (for example by department)until it is verified that it works correctly.

Correct Answer

verifed

verified

What are the three primary variables (or triple constraints) in any project?


A) Time,cost,expense
B) Time,expense,requirements
C) Time,cost,scope
D) Time,cost,quality

E) All of the above
F) A) and C)

Correct Answer

verifed

verified

Project ________________ are factors considered to be true,real,or certain without proof or demonstration.

Correct Answer

verifed

verified

Off-the-shelf application software supports general business processes and does not require any specific software customization to meet the organization's needs.

A) True
B) False

Correct Answer

verifed

verified

Pilot implementation installs the new system in phases (for example by department)until it is verified that it works correctly.

A) True
B) False

Correct Answer

verifed

verified

What is the critical path?


A) The path from resource to task that passes through all critical components of a project plan
B) The path between tasks to the projects finish that passes through all critical components of a project plan
C) The path from start to finish that passes through all the tasks that are critical to completing the project in the shortest amount of time
D) The path from start to finish that passes through all the tasks that are critical to completing the project in the longest amount of time

E) A) and B)
F) A) and C)

Correct Answer

verifed

verified

What is a set of policies,procedures,standards,processes,practices,tools,techniques,and tasks that people apply to technical and management challenges?


A) SDLC
B) Methodology
C) Waterfall
D) Agile

E) All of the above
F) None of the above

Correct Answer

verifed

verified

Post-implementation reports are formal reports or audits of a project after it is up-and-running.

A) True
B) False

Correct Answer

verifed

verified

Which of the following is not one of the four gates in the RUP methodology?


A) Inception
B) Collaboration
C) Construction
D) Transition

E) B) and C)
F) A) and B)

Correct Answer

verifed

verified

What verifies that the units or pieces of code function correctly when integrated together?


A) Alpha testing
B) Development testing
C) Integration testing
D) System testing

E) A) and D)
F) All of the above

Correct Answer

verifed

verified

Which phase takes all the detailed design documents from the design phase and transforms them into the actual system?


A) Testing phase
B) Analysis phase
C) Development phase
D) Planning phase

E) All of the above
F) C) and D)

Correct Answer

verifed

verified

Project ______________ are quantifiable criteria that must be met for the project to be considered a success.

Correct Answer

verifed

verified

Objectives...

View Answer

What determines if the system satisfies the user and business requirements?


A) Alpha testing
B) Development testing
C) Integration testing
D) User acceptance testing

E) A) and B)
F) All of the above

Correct Answer

verifed

verified

The project managers are individuals and organizations actively involved in the project or whose interests might be affected as a result of project execution or project completion.

A) True
B) False

Correct Answer

verifed

verified

The rapid application development methodology emphasizes extensive user involvement in the rapid and evolutionary construction of working __________ of a system to accelerate the systems development process.

Correct Answer

verifed

verified

What is the success rate for a project using the waterfall methodology?


A) 1 in 10
B) 2 in 10
C) 4 in 10
D) 8 in 10

E) All of the above
F) None of the above

Correct Answer

verifed

verified

__________ objects for information and related technology (COBIT)is a set of best practices that helps an organization to maximize the benefits of an information system,while at the same time establishing appropriate controls to ensure minimum errors.

Correct Answer

verifed

verified

Which of the following is the primary reason why companies outsource?


A) Tap outside sources of expertise
B) Concentrate resources on core business
C) Reduce headcount and related expenses
D) Better manage the costs of internal processes

E) A) and D)
F) A) and C)

Correct Answer

verifed

verified

What occurs when programmers test the system to ensure it is bug-free?


A) Alpha testing
B) Development testing
C) Integration testing
D) System testing

E) C) and D)
F) B) and D)

Correct Answer

verifed

verified

What is a person or event that is the catalyst for implementing major changes for a system to meet business changes?


A) Change controller
B) Change over
C) Change management
D) Change agent

E) None of the above
F) A) and D)

Correct Answer

verifed

verified