Correct Answer
verified
Multiple Choice
A) Political feasibility
B) Operational feasibility
C) Schedule feasibility
D) Legal feasibility
Correct Answer
verified
Multiple Choice
A) Gantt chart
B) PERT chart
C) All of the above
D) None of the above
Correct Answer
verified
Multiple Choice
A) Onshore outsourcing
B) Nearshore outsourcing
C) Offshore outsourcing
D) None of the above
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) Specific factors that can limit options.
B) Factors that are considered to be true, real, or certain without proof or demonstration.
C) Quantifiable criteria that must be met for the project to be considered a success.
D) A document issued by the project initiator or sponsor that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.
Correct Answer
verified
Multiple Choice
A) Institute change management policies
B) Seek change
C) Anticipate change
D) Stop change
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) Project management
B) Project management software
C) Scope
D) None of the above
Correct Answer
verified
Multiple Choice
A) Difficult to quantify or measure.
B) Easy to quantify and typically measured to determine the success or failure of a project.
C) The measure of the tangible and intangible benefits of an information system.
D) A periodic review of actual performance versus expected performance.
Correct Answer
verified
Multiple Choice
A) The path from resource to task that passes through all critical components of a project plan.
B) The path between tasks to the projects finish that passes through all critical components of a project plan.
C) The sequence of activities that determine the earliest date by which the project can be completed.
D) The path from start to finish that passes through all the tasks that are critical to completing the project in the longest amount of time.
Correct Answer
verified
Essay
Correct Answer
verified
View Answer
Multiple Choice
A) Vertically, horizontally
B) Horizontally, vertically
C) Vertically, Vertically
D) Horizontally, horizontally
Correct Answer
verified
Multiple Choice
A) Project manager
B) Project stakeholders
C) Executive sponsor
D) Communication plan
Correct Answer
verified
Multiple Choice
A) Delivered on time.
B) Delivered within budget.
C) Meets the business's requirements.
D) All of the above.
Correct Answer
verified
Multiple Choice
A) The distinguishing characteristics of a practicing professional (ethics) .
B) The content and structure of the profession's body of knowledge (standards) .
C) Change in business goals during project planning (management) .
D) Recognition of professional attainment (accreditation) .
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) Resource
B) Task
C) Dependency
D) Activity
Correct Answer
verified
Multiple Choice
A) Project objectives
B) Project constraints
C) Project assumptions
D) Project deliverable
Correct Answer
verified
Multiple Choice
A) Quantifiable criteria that must be met for the project to be considered a success.
B) Products, services, or processes that are not specifically a part of the project.
C) Any measurable, tangible, verifiable outcome, result or item that is produced to complete a project or part of a project.
D) Defines the work that must be completed to deliver a product with the specified features and functions.
Correct Answer
verified