Filters
Question type

Study Flashcards

Use the following data to find the total direct labor cost variance if the company produced 3,500 units during the period. Direct labor standard (4 hrs. @ $7/hr.) $ 28 per unit Actual hours worked 12,250 Actual rate per hour $ 7.50


A) $12,250 favorable.
B) $7,000 unfavorable.
C) $6,125 favorable.
D) $7,000 favorable.
E) $6,125 unfavorable.

F) All of the above
G) A) and B)

Correct Answer

verifed

verified

Based on a predicted level of production and sales of 22,000 units, a company anticipates total variable costs of $99,000, fixed costs of $30,000, and operating income of $36,000. - Based on this information, the budgeted amount of fixed costs for 20,000 units would be:


A) $90,000.
B) $30,000.
C) $99,000.
D) $150,000.
E) $66,000.

F) B) and E)
G) All of the above

Correct Answer

verifed

verified

Companies promoting continuous improvement strive to achieve ________ standards by eliminating inefficiencies and waste.

Correct Answer

verifed

verified

A favorable variance for a cost means that when compared to the budget, the actual cost is ________ than the budgeted cost.

Correct Answer

verifed

verified

The following company information is available for March. The direct materials price variance is: Direct materials purchased and used 2,500 feet @ $55 per foot Standard costs for direct materials for March production 2,600 feet @ $53 per foot


A) $5,000 favorable.
B) $5,200 unfavorable.
C) $5,000 unfavorable.
D) $300 favorable.
E) $5,200 favorable.

F) A) and B)
G) A) and C)

Correct Answer

verifed

verified

The difference between the actual cost incurred and the standard cost is called the:


A) Flexible variance.
B) Price variance.
C) Controllable variance.
D) Cost variance.
E) Volume variance.

F) All of the above
G) D) and E)

Correct Answer

verifed

verified

Georgia, Inc. has collected the following data on one of its products. The actual cost of the direct materials used is: Direct materials standard (4 lbs. @ $1/lb.) $ 4 per finished unit Total direct materials cost variance-unfavorable $ 13,750 Actual direct materials used 150,000 lbs. Actual finished units produced 30,000 units


A) $106,250.
B) $120,000.
C) $150,000.
D) $158,750.
E) $133,750.

F) C) and E)
G) A) and B)

Correct Answer

verifed

verified

The following information comes from the records of Barney Co. for the current period. a. Compute the direct materials price and quantity variances, direct labor rate and efficiency variances and state whether the variance is favorable or unfavorable. b. Prepare the journal entries to charge direct materials and direct labor costs to work in process and the materials and labor variances to their proper accounts.  Actual costs and quantities:  Direct materials used 37,000 feet @ $6.20 per foot  Direct labor hours used 50,660 hours  Direct labor rate per hour $16.50\begin{array} { l | l } \text { Actual costs and quantities: } & \\\hline \text { Direct materials used } \ldots \ldots \ldots \ldots \ldots \ldots \ldots & 37,000 \text { feet @ \$6.20 per foot } \\\hline \text { Direct labor hours used } \ldots \ldots \ldots \ldots \ldots \ldots & 50,660 \text { hours } \\\hline \text { Direct labor rate per hour } \ldots \ldots \ldots \ldots \ldots \ldots & \$ 16.50 \\\hline\end{array} 25,000 units were produced during the period. Standard costs and quantities per unit: Direct materials ……………………… 1.5 ft. @ $6.10 per ft. Direct labor …………………………... 2 hours @ $17 per hour

Correct Answer

verifed

verified

None...

View Answer

Standard material costs, standard labor costs, and standard overhead costs can be obtained from standard cost tables published by the Institute of Management Accountants.

A) True
B) False

Correct Answer

verifed

verified

When computing a price variance, the price is held constant.

A) True
B) False

Correct Answer

verifed

verified

Within the same flexible budget performance report, it is impossible to have both favorable and unfavorable variances.

A) True
B) False

Correct Answer

verifed

verified

Identify the situation below that will result in a favorable variance.


A) Actual costs are higher than budgeted costs.
B) Actual income is lower than expected income.
C) Actual revenue is higher than budgeted revenue.
D) Actual expenses are higher than budgeted expenses.
E) Actual revenue is lower than budgeted revenue.

F) D) and E)
G) A) and E)

Correct Answer

verifed

verified

Standard costs can be used by management to assess the reasonableness of actual costs incurred.

A) True
B) False

Correct Answer

verifed

verified

Fletcher Company collected the following data regarding production of one of its products. Compute the variable overhead spending variance.  Direct labor stendard (2 hrs. @ $12.75/hr.)  $25.50per finished unit Actual direct labor hours 81,500 hrs Budgeted units 42,000unitsActual finished units produced40,000unitsStandad variable OH rate (2 hrs. @ $14.30/hr) $28.60per finished unitStandard fixed OH rate ($ 336,000 / 42,000 units) $8.00per unitActual cost of variable overhead costs incurred$1,140,000Actual cost of fixed overhead costs incurred$338,000\begin{array}{lll}\text { Direct labor stendard (2 hrs. @ } \$ 12.75 / \mathrm{hr} \text {.) } & \$ 25.50 &\text {per finished unit}\\\text { Actual direct labor hours } & 81,500&\text { hrs}\\\text { Budgeted units } & 42,000&\text {units}\\\text {Actual finished units produced}&40,000&\text {units}\\\text {Standad variable OH rate (2 hrs. @ \$14.30/hr) }&\$28.60&\text {per finished unit}\\\text {Standard fixed OH rate (\$ 336,000 / 42,000 units) }&\$8.00 &\text {per unit}\\\text {Actual cost of variable overhead costs incurred}&\$1,140,000\\\text {Actual cost of fixed overhead costs incurred} &\$ 338,000 \end{array}


A) $4,000 favorable.
B) $21,450 favorable.
C) $4,000 unfavorable.
D) $21,450 unfavorable..
E) $25,450 favorable.

F) None of the above
G) A) and B)

Correct Answer

verifed

verified

Which department is often responsible for the direct materials price variance?


A) The accounting department.
B) The budgeting department.
C) The purchasing department.
D) The finance department.
E) The production department.

F) A) and B)
G) A) and C)

Correct Answer

verifed

verified

Levelor Company's flexible budget shows $10,710 of overhead at 75% of capacity, which was the operating level achieved during May. However, the company applied overhead to production during May at a rate of $2.00 per direct labor hour based on a budgeted operating level of 6,120 direct labor hours (90% of capacity) . If overhead actually incurred was $11,183 during May, the controllable variance for the month was:


A) $473 unfavorable.
B) $1,530 unfavorable.
C) $1,057 favorable.
D) $1,530 favorable.
E) $473 favorable.

F) A) and B)
G) A) and E)

Correct Answer

verifed

verified

A volume variance occurs when the company operates at a different capacity level than was expected.

A) True
B) False

Correct Answer

verifed

verified

A company provided the following direct materials cost information. Compute the direct materials quantity variance. Standard costs assigned:\text {Standard costs assigned:} Direct materials standard cost (405,000 units @$2.00/unit)  $810,000 Actual costs:Direct Materials costs incurred ( 403,750 units@$2.20/unit)  $888,250\begin{array}{llr} \text {Direct materials standard cost (405,000 units @\$2.00/unit) } & \$ 810,000\\ \text { Actual costs:} &\\ \text {Direct Materials costs incurred ( 403,750 units@\$2.20/unit) } &\$ 888,250 \end{array}


A) $78,250 Favorable.
B) $2.500 Favorable.
C) $2,750 Unfavorable
D) $2,500 Unfavorable.
E) $2,750 Favorable.

F) B) and D)
G) C) and D)

Correct Answer

verifed

verified

A company's flexible budget for the range of 35,000 units to 45,000 units of production showed variable overhead costs of $2 per unit and fixed overhead costs of $72,000. The company incurred total overhead costs of $148,800 while operating at a volume of 40,000 units. The total controllable cost variance is:


A) $6,800 unfavorable.
B) $3,200 unfavorable.
C) $3,200 favorable.
D) $10,000 favorable.
E) $6,800 favorable.

F) C) and D)
G) B) and D)

Correct Answer

verifed

verified

A cost variance is the difference between actual cost and standard cost.

A) True
B) False

Correct Answer

verifed

verified

Showing 101 - 120 of 223

Related Exams

Show Answer